Issues with Forecast AI - Event - April 2026

Hi All,

I used Forecast AI - Event for a 3 hour Competitive Gran Fondo event help in early April of 2026 and followed my training plan with success.

I had a rest week and then generated a new Forecast AI - Event plan for a 4 hour Competitive Gran Fondo event scheduled for August. I have been following this plan for a few days and have noticed the following:

  1. Multiple high intensity days during the week.
  2. Xert prescribing workouts that fall short of the weekly and daily time I have available.
  3. Each and every of the forecasted workouts are listed as unproductive.

Notes:

  1. I had my last breakthrough 2 weeks ago.
  2. My power meter failed during the early April Gran Fondo so I flagged that activity.
  3. I have moved my decay method from Optimal to None - Training Load Matched.

Is there something I have done wrong with setting up my plan or is Xert having a moment?

You can use FitFileTools.com to strip the incomplete power data and let that ride be analyzed by HRDM.

Post a screenshot of your forecast chart.

It is more that every single workout in my plan is listed as unproductive. It makes zero sense to me as to why.

Appears to be a bug as the XSS values are a close match to target.

1 Like

Yep - looks to be a bug in the suitability score when comparing the XSS actuals from the workouts/activities to the XSS recommendations… We’ll take a closer look at that & get it sorted. Cheers